Sl. No |
Year |
Project Name |
Taluk |
Village |
Project Cost (in Cr) |
Beneficiary |
Status |
1 |
2018-19 |
Deepening of drinking water open well near PHC, Krishanapuram, Vengalam Panchayat |
Veppanthattai |
Krishanapuram |
0.03 |
5000 |
Completed |
2 |
2018-19 |
Protective fencing of kudineer eri in Siruganpur Panchayat adjacent to Varagupadi |
Alathur |
Siruganpur Panchayat adjacent to Varagupadi |
0.025 |
50 |
Completed |
3 |
2018-19 |
New borewell with submercible motor in Girls hostel at Padalur (E) Village, Alathur Taluk, Peramblaur District. |
Alathur |
Padalur (E) Village |
0.013 |
55 |
Completed |
4 |
2018-19 |
BC Hostel construction of Underground drainage & Drinking water supply connection at Opposite GH in Peramblaur District. |
Perambalur |
Perambalur (Opposite GH) |
0.041 |
110 |
Completed |
5 |
2018-19 |
Providing water supply to mines affected villages in Alathur,Perambalur & Veppanthattai Unions,CWSS to 306 habitations in Perambalur District |
Perambalur |
Alathur, Perambalur & Veppanthattai Unions |
0.378 |
234700 |
Completed |
6 |
2018-19 |
The restoration of damaged CI Pipeline,Pump set and Electrical accessories in the infiltration well at Kollidam river due to heavy flood during August-2018 under CWSS at Thallakudi village in Perambalur district. |
Perambalur |
Thallakudi |
0.155 |
154187 |
Completed |
7 |
2018-19 |
Supply, Delivery, laying and joining of 140 MM PVC pipe for connecting main from infiltration well to Collector well at Head works in river Kollidam under CWSS to 116 Habitations in Perambalur and Trichy District |
Perambalur |
Perambalur |
0.021 |
480 |
Completed |
8 |
2020-21 |
Construction of 30,000 litres capacity sump at southmadavi village for providing water supply to Varagupadi and Siruganpur habitations of Alathur Union covered under CWSS to 645 habitations in Ariyalur and Perambalur Disticts for the Year 2020-2021 |
Perambalur |
Perambalur |
0.07 |
3200 |
Completed |
|
|
|
|
Total |
0.733 |
397782 |
|